Impulse Migration

Caerphilly RAG Status Dashboard

Report Date: 1 February 2026 | Overall Status: Amber
# Dimension RAG Criteria / Evidence Impact / Risk Mitigation / Next Action Owner Due Date Trend
1 Schedule / Timeline Green All March training & data cuts on track; GOSS 14 Feb prepped. No slippage. Low Monitor summer peak (Jul–Sep). Liz Ongoing Stable
2 Data Migration & Cleanse Amber Address cleanse meeting pending; spreadsheet inventory incomplete; exceptions not fully highlighted. Medium Kick-off cleanse meeting this week; complete inventory by 10 Feb. Lewis / Tom 10 Feb 2026 Worsening
3 Resources / Training Amber Training wave starts March; Bev/sysadmin slots booked; but 240 users = high volume risk. Medium Finalize user roles/licenses list; train-the-trainer plan. Liz / Bev End Feb Stable
4 Budget / Costs Green Within forecast; no variances noted yet. Low Track CACI on-site & extra days costs. Finance lead Monthly Stable
5 Scope / Deliverables Amber Parent portal priority not locked; some outputs (e.g., ALN panels) post-April; manual workarounds high. High Confirm parent portal timeline with CACI; prioritize over HuB short-term. Lewis / CACI Mid Feb Improving
6 Risks & Issues Red Manual workload April–June could cause burnout; data gaps if cleanse delayed; summer peak clash. High Resource capacity plan; contingency for manual hump; escalate to SMT if cleanse slips. PM / SMT 7 Feb Escalating
7 Stakeholder / Comms Green Lisa owns; front-page notice planned; schools engagement starting. Low Finalize schools comms for 5 ALN sites (Louisa). Lisa / Louisa End Feb Stable

Key Metrics

Completion 42%
Risk Level Medium

RAG Distribution

3
Green
3
Amber
1
Red

Upcoming Milestones

10 Feb - Data cleanse inventory

Lewis / Tom

14 Feb - GOSS prep

Liz

End Feb - Training plan

Liz / Bev